It has 2 days of work logged with 1 day remaining, so its progress is 2 / (2 + 1).
If a sub-issue does not have time tracking information, it is counted in as an average sub-issue, based on the mean total time (time spent + remaining estimate) of its siblings.If time tracking is used and all issues have an estimate (either original estimate or remaining estimate), the estimates and total work logged are summed up and the progress is calculated as the total completion %: (Total Time Spent) / (Total Time Spent + Total Remaining Estimate).If the issue and its sub-issues do not have estimates or work logged (or if time tracking is turned off), the progress is calculated as the average of the sub-issues' progresses.If the issue's Resolution field is not empty, and Apply Resolution is turned on, the progress is 100% - regardless of the sub-issues' progress.Otherwise, if the issue has time tracking information, the progress is calculated proportionally to this issue completion %: (Time Spent) / (Time Spent + Remaining Estimate)Ĭalculating Progress for Issue with Sub-Issues.If the issue's Resolution field is not empty, and Apply Resolution is turned on, the progress is 100%.When Issue Progress is based on Time Tracking within a Progress column, the progress is calculated based on the issue's Resolution field, time tracking data, and the progress of its sub-issues.Ĭalculating Progress for Issue Without Sub-Issues